By Elijah Polance
UConn Journalism
In 2016, the Metropolitan District Commission (MDC) began constructing a storage tunnel to hold untreated sewage and rainwater during storms. It is called the South Hartford Conveyance and Storage Tunnel and was supposed to be completed by the end of 2023. But delays with the contractor and a related lawsuit advanced the predicted operation to fall 2026.
The delays were due to excess water underground during drilling, said Susan Negrelli, director of engineering and planning for the MDC. She said that with such large-scale projects, there are inevitable unknown factors that cannot be accounted for beforehand.
“The contractor claimed they had more water that they had to deal with in the tunnel as they were excavating than the design plans showed,” Negrelli said. “So that slowed them down considerably.”
That contractor, Kenny Obayashi, sued the MDC, which announced the parties settled in March by agreeing to about $51 million for additional change orders, the MDC reported in a statement. The tunnel contract was initially priced at $279 million, but the total cost is now listed as $335 million.
MDC spokesman Nick Salemi said in a statement sent to all media, “It is not uncommon for owners, and by extension its contractors, to encounter differing site conditions in the construction of deep rock tunnels, in this case a tunnel approximately 200 feet below the surface.” The MDC said Obayashi’s company, KOJV, had submitted several change orders for the tunnel’s three reaches. The orders totaled more than $100 million. MDC agreed with some of the claims but disputed the amount of the extra costs. All but $28 million of the $51 million agreed upon was eligible for Clean Water Fund grants and loan funding.
The tunnel measures four miles long and runs 200 feet underground, with enough space for the tunnel’s 18-foot diameter. It was carried out with a boring machine named IRIS, which began drilling in 2019 and finished in 2022. It will hold waste from West Hartford and southern areas of Hartford.
Nick Salemi, spokesperson for the MDC, said delays in the drilling process set back construction of the water pump station. He said the pump station could not begin construction until the tunnel was finished.
“The tunnel portion went slower than anticipated, which pushed back some of the other work,” Salemi said. “The pump station is in construction right now.” The station will transport the stored waste and stormwater upwards and across a road to the Hartford Water Pollution Treatment Facility. Upon treatment, the cleaned water will be released into the Connecticut River.
Negrelli said the pump station’s original planned completion date of July 2026 may may be pushed later.
“We’re dealing with some delays with some electrical equipment,” Negrelli said while showing journalists the pump site in April. “So we’re thinking about the late summer or fall of 2026.”
Salemi said the pump station relies on physics to move the water upwards. “The whole thing works on gravity,” he said. “There’s not a lot of electricity to get it 200 feet to the plant. The pump station pumps the water up across the street to the treatment plant.”
Construction of the pump station is being carried out by the engineering company Arcadis, which has done work for other MDC projects. Greg Bazydola, Arcadis project manager for the pump station, said the work balances factors like automation, preventing excess water pressure buildup, and avoiding excess humidity, which can damage equipment.
Two shafts in that station extend underground to meet the pump. The first shaft was where the tunnel drilling began with a crane lowering IRIS to the necessary depth. Now that the tunnel itself has been dug, this shaft will be repurposed to screen large solids and grit from water stored in the tunnel.
“You want to protect those pumps that are down there from big debris so it doesn’t wear anything,” Bazydola said.
Eventually, more waste from the Franklin Avenue area of South Hartford will also flow into this pump station. Those conduits have yet to built. That project is called Contract Four, also called the East Conduits. The Franklin Avenue conduits do not need to be finished for the tunnel to work.
TOP IMAGE: At the future pump site, a shaft goes down 200 feet to meet the end of the waste tunnel. Photo by Christine Woodside